As a product design agency, one of the most common questions we hear from clients is: “Can I get my product designed, developed, and delivered in time for Christmas?” For instance, many clients approach us mid-year with tight deadlines, wondering if their product can hit the shelves in time. Unfortunately, the answer is often no. While it depends on the type of product, it’s crucial to understand the steps involved and how timelines add up.

To help visualize this process, we often work backward from the delivery date. Let’s explore the key phases of bringing a product to market and the time each stage typically requires.

1. Shipping and Importing: 4 Weeks

For most products manufactured offshore, shipping is a fixed and non-negotiable part of the timeline. For example, shipping a product from Asia to Australia takes approximately four weeks. This includes transit time and the process of importing goods through customs. So, right off the bat, you’re looking at one month just for shipping.

2. Manufacturing: 4 to 6 Weeks

Once the design is finalized, and a factory is ready to produce the product, the actual manufacturing run can take anywhere from four to six weeks, depending on the product's complexity and how many units are required. This phase includes assembly, quality checks, and packaging. Combined with shipping, this brings us to roughly two to three months of production time.

3. Sampling and Prototyping: 2 to 4 Weeks

Before full-scale manufacturing begins, samples or prototypes are created to validate the design and ensure the product meets expectations. Sampling usually adds another two to four weeks, pushing the timeline closer to three months or more. Note that this is a best case scenario for a custom product typically, and complex products can take a lot longer as more iterations may be required, and each iteration taking a little longer.

 

4. Tooling Setup: 6 to 12 Weeks

For products that require custom tooling—such as injection molds, die casts, or other specialized equipment—an additional six to twelve weeks should be factored into the timeline. Tooling setup includes designing, producing, and testing the tools to ensure they meet the required specifications. This step is crucial for mass production, as it directly impacts the quality and efficiency of manufacturing.

5. Factory Setup and Engagement: Variable

If you already have a trusted factory partner, this step can be streamlined. However, if a new factory needs to be sourced, vetted, and engaged, this can add weeks or even months to the timeline. Finding the right manufacturing partner is critical to ensure quality and reliability, so it’s not a step to rush.

6. Design, Development, and Compliance: 6 to 12+ Months

This phase is where the magic happens—but it’s also the most time-consuming. Designing, testing, and validating a product can take anywhere from six months to over a year, depending on the product’s complexity. Compliance testing, such as safety certifications or industry standards, adds another layer of time and detail to this stage.

How the Timeline Adds Up

For simpler products, you’re looking at a total of 6 to 12 months from initial concept to delivery. For more complex products, the timeline can extend to 1 to 2 years or more. The exact duration depends on factors like the type of product, the number of design iterations required, and the efficiency of your supply chain.

Plan Early, Launch Successfully

The key takeaway? Start planning as early as possible. By understanding the steps involved and working with a trusted product design agency, you can set realistic goals and avoid last-minute stress. Whether you’re aiming to launch in time for the holiday season or a major trade show, knowing the timeline ensures you’re prepared for every stage of the journey.

Need help bringing your product idea to life? Contact us today to discuss your project and timeline. Together, we’ll turn your vision into a reality—on time and on budget.

 

You may also like

Why You Need a Product Design Engineer
Why You Need a Product Design Engineer
1 February, 2024

At HonePD, our team of product design engineers are crucial for your product design project. As product design engineers...

6 Key Characteristics of Outstanding Product Design
6 Key Characteristics of Outstanding Product Design
30 November, 2023

In an ever-competitive market, quality product design is no longer a luxury—it's a necessity. As you navigate the intric...

Flying Over Roads Well Travelled
Flying Over Roads Well Travelled
28 February, 2019

Late last month Boeing successfully tested their first prototype for an electric flying car. The company has committed t...